Construction activity is resuming April 28 and continues until May 30 at the new Pinehurst Station. Started Mon Apr 28 Until Sat May 31 Construction work is taking place at the new Pinehurst Station. Trains will share one track through the Shoreline South/148th Station requiring passengers to use the alternate side of the platform during construction hours. Work will take place evenings, Monday through Friday, from 7 p.m. until 5 a.m., and all day on Saturday and Sunday. Trains will arrive about every 12 minutes beginning at 5:30 p.m.
Phase 1: March 24 through April 13 - Complete
Phase 2: April 28 through May 30 - Trains will be using the Angle Lake platform.
During the weekend of May 2-4 there will be construction in the area but it will not require the trains to share one track.
No work will be done May 17-18, and during the Memorial Day weekend of May 24-26